A 58-ton gas prechitor designed for the Amur Gas Processing Plant needs was unloaded in soil weakened by flooding conditions (difficulties with the crane equipment use).
Project implementation year: 2019
Customer: The Linde Group
Description
To eliminate the damage risks to expensive equipment, it was decided to attract the "Recovery Train EDK-2000" from Russian Railways for unloading. The car arrived at the Mikhailo-Chesnokovskaya station. Preparation for the crane unloading and deployment took 4 hours, after which Kargo Link specialists, together with the staff of the recovery train, began unloading the equipment. The equipment was loaded onto vehicles for further transportation to the AGP construction site.
Result
The prechitor was safely and efficiently unloaded on time.